Requirements and Environmental Design for LCD Splicing Wall
Number of views:1792order Release Date:2020-11-26
To ensure the smooth implementation of the LCD splicing wall construction project and the normal operation of the system equipment, the construction of the equipment must meet the following environmental conditions:

1、 Power supply

Considering that the system may encounter special situations where there may be a current surge due to the interruption of power supply, the splicing unit itself has a power protection design to ensure the normal and safe operation of the equipment.

1. The power supply voltage should be stable and reliable, especially to prevent immediate power up after power failure. Therefore, in principle, the power supply of the splicing system must be powered by a corresponding power UPS.

2. The splicing system, image controller, and control PC require in-phase power supply.

3. The system equipment should have good grounding, with a grounding resistance of less than 2 Ω, to ensure that the equipment is not damaged in the event of special conditions such as lightning strikes.

4. The power supply of the system is AC 220V ± 5%; Use a three eye socket with a protective grounding wire; The number of sockets is related to the number of splicing units

2、 Light requirements

1. If the windows in the control room are large, direct sunlight should be avoided and curtains should be used to block the light. The curtains should be dark in color.

2. It is recommended to use recessed tube lights for lighting. The lights should not be directly aimed at the screen direction and should be kept at a distance of 3 meters from the screen to avoid affecting the projection effect.

3、 Air conditioning requirements

1. There should be good temperature control and heat dissipation measures in the maintenance channel behind the splicing screen panel. If it is a central air conditioning system, there should be air conditioning inlet and outlet ports. If there is no central air conditioning system, specialized air conditioning should be added, and the power of the air conditioning system depends on the size of the large screen.

2. The temperature inside the maintenance channel and the temperature in the control room of the splicing curtain wall should be controllable and kept basically the same.

4、 Installation requirements

② The cabinet base is usually in direct contact with the anti-static floor to ensure that the ground can withstand gravity for a long time without deformation.

① The installation ground requires a flat and sturdy surface, strong load-bearing capacity, and is not easily deformed.

5、 Requirements for wiring and trunking

1. If it is a fixed floor such as floor tiles or composite wood flooring, it is required that there is a wiring groove between the signal source (computer RGB signal, video signal) and the control computer to the graphics controller (or projector interface), and the shorter the wiring distance, the better.

2. Weak current cables (RGB, video, network, serial port, mouse and keyboard extension cables, etc.) should be routed separately from strong current cables to avoid signal interference. If using cable trays, it is not possible to share one cable tray, and different cable trays should be used for separate wiring.

3. If it is an anti-static floor, holes should be opened at the wiring outlet to leave cable outlets.

6、 System environment

1. The temperature and humidity of the air conditioner before and after splicing the screen should be adjusted to the same scale to ensure the heat dissipation of the splicing wall and the flatness of the splicing screen

2. The fire sprinkler shall be as far away from the splicing wall as possible, and spray extinguishing agent shall be used.

3. The splicing curtain wall room requires cleanliness and dust prevention.

4. The back of the splicing system is a maintenance channel, and the width of the maintenance channel is generally not less than 0.60 meters

5. Large screen rooms require good temperature and humidity control. The working environment temperature is 0 ℃ -40 ℃, and the relative humidity is 10% -90%. There should be air conditioning behind the spliced curtain wall.

7、 Requirements for decoration and equipment location of operation console (room)

1. The placement of the image controller should be located in the aisle (inside the cabinet) next to or behind the curtain wall, and should be as close as possible to the projection box

2. The control computer should be located as close as possible to the opposite direction of the splicing screen and at a suitable distance from it for debugging, color adjustment, and other operations.

3. The position of the operation control computer should be directly opposite the splicing screen, and it is required that the operator can easily and intuitively see the operation of the splicing screen. If there is a dedicated partitioned operation control room, there should be transparent glass between the operation control room and the large screen display room for easy viewing by the operator.


Contact Us
Address: Building B, Lihao Yongda Technology Park, No.1 Dongfang Avenue, Guangming District, Shenzhen
Phone: 0755-23576861
24-hour service hotline: 139 2371 0018

QR code
CopyRight ? 2017 Shenzhen Jintong Display Technology Co., Ltd. All Right Reserved
展開
  • Tel

  • 075523576861
QR code
亚洲自偷自偷偷色无码中文| 亚洲色大成网站www| 亚洲午夜精品一区二区| www国产内插视频| 色94色欧美sute亚洲线路二| 少妇又紧又色又爽又刺激视频| 亚洲色偷偷色噜噜狠狠99网| 蜜桃臀无码内射一区二区三区| 亚洲午夜久久久久妓女影院 | 精品少妇人妻av免费久久洗澡| 久久精品国产亚洲av大全| 老师脱了内裤让我进去| 久热综合在线亚洲精品| 亚洲欧洲∨国产一区二区三区| 红桃影视成人免费| 久久99热狠狠色精品一区| 中文字幕无码免费久久| 色综合av综合无码综合网站| 日韩欧精品无码视频无删节| 狠狠色噜噜狠狠狠狠888奇禾| 久久精品国产亚洲av久| 中文字幕美人妻亅u乚一596 | 狠狠色婷婷久久综合频道日韩| 国产在线国偷精品免费看| 牲欲强的熟妇农村老妇女| 亚洲熟妇av一区二区三区| 樱桃视频影院在线播放| 疯狂做受xxxx高潮视频免费| 天天色影网| 天堂网在线最新版www中文网| 中国浓毛少妇毛茸茸| 亚洲avav天堂av在线网毛片| 成人欧美一区二区三区黑人免费| 日日噜噜夜夜狠狠va视频| 亚洲av永久无码天堂网| 婷婷四房播播| 国产精品亚洲日韩欧美色窝窝色欲| 国产艳妇av在线| 三上悠亚av影院在线看| 男受被做哭激烈娇喘gv视频 | 乱人伦人妻精品一区二区|